![]() Renewable EnergyBord na Móna Energy Limited is the majority (88.5%) shareholder in Renewable Energy Ireland Ltd., which established Ireland‘s first commercial windfarm on cutaway blanket bog at Bellacorick, Co. Mayo in 1992. The windfarm comprises 21 wind turbines, with a total installed capacity of 6.45 MW. The mean annual wind speed at a height of 30 metres is 7.28 m/sec. The windfarm generates 17 million units (kWh) of electricity each year, and has an average availability of 98%. The Bellacorick area is remote, with a flat, open aspect. The availability of substantial additional areas of cutaway blanket bog, along with a 110 kV link to the adjacent thermal power station, mean that the capacity of the windfarm could be expanded considerably. Bord na Móna Energy Limited is seeking consent to increase the number of wind turbines on the site. Environmental benefits include the generation of electricity without the release of any CO2, SO2, NOx or dust. |